Central Water Treatment Plant

The Central Water Treatment Plant (WTP) is being constructed at 1290 North Frontage Road, which is next to the existing Nitrate Treatment Plant and Ground Storage Reservoir owned by the City. Start-up of the Central WTP is planned for January 2027 with final completion in Spring 2027. The contractor is Magney Construction. 

The Central WTP will remove PFAS from Wells 3, 5 and 7. The location of Well 7 (9th Street and Ashland Street) requires a raw watermain to be extended from Well 7 to the Central WTP. This project was constructed and completed by a different contractor, A-1 Excavating. 

The construction of the new Central PFAS Water Treatment Plant and water lines started summer 2025. View below for construction updates.

Construction Updates

 

 

  • Magney Construction and their subcontractors completed the roofing, masonry, and most of the windows and floor slabs.
  • Made connections to existing watermains in North Frontage Road and had temporary road closures from October 19-30. N Frontage Rd closure letter mailed to the surrounding neighborhood and businesses.
  • The first two of the twelve granular activated carbon (GAC) pressure filter vessels were delivered in mid-October, and they will continue to be delivered in pairs every couple of weeks through the end of the year.

  • On November 19, 2026, Magney construction successfully and safely brought in one of the Newterra vessels inside the CWTP.